Project facts

Client: Pader Entsorgung GmbH & Co KG

Project Period: 2003 - 2005

Capacity: 85,000 t/y

Mechanical preparation of 85,000 t/y commercial and domestic waste for secondary fuel production. Extensive separation technology including infra-red separation and ballistic separation, production of secondary fuel in accordance with the regulations of the Federal Association of secondary fuels, independent supervision of the construction.

The services included preliminary planning and final design, contract elaboration, construction supervision, start-up and trial operation, supervision and assistance during the warranty period.